Question 1
Following a VFD shutdown, a qualified technician locks out all supplies and completes the required restart checks. The manufacturer's access procedure requires a wait of at least 10 minutes and a DC-bus reading below 50 V at designated test points. After 12 minutes, an appropriate, verified meter reads 72 V DC; the display is dark. What should govern access to the bus terminals?
Show answer & explanation
Correct answer: D - The measured bus voltage, which remains above the permitted access threshold.